This edition of the HCO quizz is about Organisation. Try it.

The numbered items is a set of statements about the Organisation Component. The next bullet list is a list of roles from the Project Management Team. For each numbered statement select the appropriate role from the bullet list that applies to that statement. A selection from the Bullet list may be used more than once or not at all. Which one of the preselected answers is correct?
  1. Aims to achieve the results required by the Senior User within the cost and time parameters for which the Executive is accountable
  2. Checking that the Project Approach is technically correct.
  3. Will normally come from the customer organisation, but there will be projects where the role comes from the supplier.
  4. Checking the impact of any changes to the Business Case.
  5. Ensuring that the project produces products that meet user requirements.
  6. Checking that the Project Approach is in line with corporate or programme strategy.
  7. Prime responsibility is to ensure production of those products defined by the Project Manager to an appropriate quality in a timescale and at a cost acceptable to the Project Board
  8. Monitoring and controlling the progress of the business change at a strategic level.
  • Executive
  • Senior User
  • Senior Supplier
  • Project Assurance (Executive)
  • Project Assurance (Senior User)
  • Project Assurance (Senior Supplier)
  • Project Manager
  • Team Managers